Scheduled tasks are not running
-
For some reason, none of our scheduled tasks are running. It looks like they stopped running when we installed ProGet 4.6.2. If I try to run them manually, I just get a clock cursor for a moment, then it is done, without having run the task.
Any ideas?
Product: ProGet
Version: 4.6.2
-
The ProGet service must be running for the scheduled tasks to run; can you verify whether that's the case or not?
Regardless, you should consider upgrading to the latest v4.6.X (currently v4.6.7) - there were some issues w/ v4.6.2 and over-logging that slowed performance down greatly and may result in other issues like the one you're experiencing.
-
OK, I will upgrade to the latest version.
It turns out the ProGet service wasn't running. I hadn't even realized it because the Web site and NuGet/NPM feeds were working normally. Starting the service was all that was needed to get those tasks running. Thanks