Welcome to the Inedo Forums! Check out the Forums Guide for help getting started.
If you are experiencing any issues with the forum software, please visit the Contact Form on our website and let us know!
Scheduled tasks are not running
-
For some reason, none of our scheduled tasks are running. It looks like they stopped running when we installed ProGet 4.6.2. If I try to run them manually, I just get a clock cursor for a moment, then it is done, without having run the task.
Any ideas?
Product: ProGet
Version: 4.6.2 -
The ProGet service must be running for the scheduled tasks to run; can you verify whether that's the case or not?
Regardless, you should consider upgrading to the latest v4.6.X (currently v4.6.7) - there were some issues w/ v4.6.2 and over-logging that slowed performance down greatly and may result in other issues like the one you're experiencing.
-
OK, I will upgrade to the latest version.
It turns out the ProGet service wasn't running. I hadn't even realized it because the Web site and NuGet/NPM feeds were working normally. Starting the service was all that was needed to get those tasks running. Thanks
Hello! It looks like you're interested in this conversation, but you don't have an account yet.
Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.
With your input, this post could be even better 💗
Register Login