    [OTTER] long time to change status for server and assigned server roles

    Scheduled Pinned Locked Moved Support
    5 Posts 2 Posters 10 Views
    Loading More Posts
    • Oldest to Newest
    • Newest to Oldest
    • Most Votes
    Reply
    • Reply as topic
    Log in to reply
    This topic has been deleted. Only users with topic management privileges can see it.
    • P Offline
      philippe.camelio_3885
      last edited by

      Hello,

      Just to report it takes a long time (> 2 mn) to change the status of agent and assigned server roles after a successfull remediation

      72d4f71b-244b-433d-ba8d-532ab968091b-image.png

      This delay is annoying, previous versions did not have it.
      I am using docker version (2023.3)

      Any suggestion to improve this behaviour if it is not a bug ?

      Best regards
      PhilippeC.

      atrippA 1 Reply Last reply Reply Quote 0
      • atrippA Offline
        atripp inedo-engineer @philippe.camelio_3885
        last edited by

        Hi @philippe-camelio_3885 , what was the previous version? Otter 2022?

        P 1 Reply Last reply Reply Quote 0
        • P Offline
          philippe.camelio_3885 @atripp
          last edited by

          Hello @atripp
          No, the older one Version 3.0.24 👴

          atrippA 1 Reply Last reply Reply Quote 0
          • atrippA Offline
            atripp inedo-engineer @philippe.camelio_3885
            last edited by

            Thanks @philippe-camelio_3885; can you walk me through the scenario of what you're doing? The "Error" status doesn't seem quite right....

            Otherwise, the "status" on a server can be a complicated thing in Otter sometimes, since it represents a few things.

            Under Admin > Service, you can manually trigger some of the Task Runners that are responsible for changing status. Can you identify which one needs to be run in order to get Otter to report the desired status.

            Once we understand what you're doing, and what task isn't being run by the service on time, we can try to fix

            1 Reply Last reply Reply Quote 0
            • P Offline
              philippe.camelio_3885
              last edited by

              Hum, difficult to reproduce.
              it happens with new server.
              I will see if I can make a simple reproducible test case

              1 Reply Last reply Reply Quote 0

              Hello! It looks like you're interested in this conversation, but you don't have an account yet.

              Getting fed up of having to scroll through the same posts each visit? When you register for an account, you'll always come back to exactly where you were before, and choose to be notified of new replies (either via email, or push notification). You'll also be able to save bookmarks and upvote posts to show your appreciation to other community members.

              With your input, this post could be even better 💗

              Register Login
              • 1 / 1
              • First post
                Last post
              Inedo Website Home • Support Home • Code of Conduct • Forums Guide • Documentation